PHƯƠNG MAI 3 WIND FARM PROJECT– SPEED UP TO GENERATE POWER ON SCHEDULE



It was told that in Tây Sơn – Bình Định, 230 years ago in the Spring of Mậu Thân 1789, Emperor Quang Trung asked the soldiers to celebrate premature Tet and then marched quickly to the north to liberate Thăng Long, making the victory in Ngọc Hồi – Đống Đa, defeated 290,000 Qing soldiers, marking a historic milestone in the anti-invasion history of our nation.
And now in 2019, on the same land of Quy Nhơn – Bình Định, the Central Wind Power Joint Stock Company (CWP) – a member of HALCOM Việt Nam JSC, the investor of the Wind Farm Project, is following the spirit of speediness the ancestors by fulfilling important work items of the Phương Mai 3 Wind Farm within 6 months only.
In September 2018, CWP signed the contract for “Supply, Transportation and Installation of Wind Turbines, Operation and Maintenance Services” under the Phương Mai 3 Wind Farm Project with Siemens Gamesa Renewable Energy (Siemens Gamesa), the biggest supplier of wind power and renewable energy equipment and technology in the world.


In October 2018, the contract for 110kV Substation and Cables (E-BOP) with Hanoi Telecommunication and Power Company (Hatec) was signed. The survey, design and construction of the 110kV substation and cables will be completed by Hatec within 28 weeks from the effective date of the contract.