Can Tho 923 Road and Real Estate Project

Objectives:

Upgrade and rehabilitate the section from Phong Điền – Ba Se – NH91 (Km11+326.8 – Km25+680) with total length of about 14.5 km; pavement widening from 3m to 7m, subgrade widening from 4m to 12m in accordance with the flat area class III standard TCVN 4054 -2005. Rehabilitate and construct 9 existing steel bridges on the road section and 30 culverts. The upgraded section will act as a bypass of Can Tho city and accommodate most of the transit trips through the city from Ho Chi Minh city to the western Mekong delta provinces and from eastern Mekong delta provinces to the western Mekong delta provinces which were formerly made on the National Highway 91B

Location:
Section from Phong Dien – Ba Se – NH91 (Km11+326.8 – km25+680) with total length of about 14.3km

Total investment : 1,750 billion dongs

Progress :

  • 2015:
    • Geological and topographic survey, mapping and travel forecast;
    • Perform the Project financial, economic and investment analysis;
    • Propose the project investment;
  • 2016:
    • Establish a joint venture of the investment project;
    • Work with financial institutions;
    • Project commencement

Investment form: Build – Transfer (BT)