Halcom Vietnam releases the EPC bidding documents for Hau Giang Solar Power Plant

Hanoi – 29 April, 2020, Halcom Vietnam JSC. released the EPC (Engineering, Procurement and Construction) bidding documents for Hau Giang Solar Power Plant (capacity: 29MWac).

The plant is located at Hoa An commune, Phung Hiep district, Hau Giang province, Vietnam. VKT-Hoa An, a member of Halcom Vietnam, owns the project. This is the second renewable energy project by Halcom Vietnam, after Phuong Mai 3 Wind Power Plant (Nhon Hoi economic zone, Binh Dinh province).

Hau Giang Solar Power Plant project started its first steps, and the construction is planned as below:

  • End of May, 2020: EPC contractor selection
  • Early June, 2020: contract signing, starting plant construction
  • Construction period: 6 months
  • December, 2020: COD